Today Federal Ministers offered an update on the AOPS Project.
The first 2 of 7 phases of the 288 million definition contract were completed on time and on budget. This contract was announced in March 2013. an additional 2 phases of the 7 phases have now authorized, valued at 53 million. (presumably phases 3 and 4) Phases 3 and 4 Include
Engineering Design Phase 2 – This task will include the system engineering activities, integrated logistical support analysis and supplier engagement activities that are necessary to demonstrate that the Arctic/Offshore patrol ship design is a complete and integrated solution that meets all the contract design specification requirements with acceptable risk and within the cost and schedule constraints.
Engineering Design Phase 3 – This task will include the system engineering activities, integrated logistic support analysis and supplier engagement activities that are necessary to demonstrate that the Arctic/Offshore patrol ship design is a complete and integrated solution that meets all of the contract design specification requirements and is ready for the start of vessel construction.
UPDATE: the 2 additional packages authorized were actually 3 and 5, Which are Engineering Design Phase 2 and the Project Implementation Proposal Development. The Project Implementation Proposal Development
Project Implementation Proposal Development – This task will encompass all the procurement, engineering, production and estimating activities required to develop the detailed project implementation proposal, including the required plans and a substantive cost for the implementation contract.
No Number of vessels has been set yet – So it still stands at the vague 6-8