Work on the Halterm Expansion has moved to Pier 9. Dredging was completed at pier 9 Mid may, and the dump scows have been used to prepare the sea bed with coarse gravel loaded at pier 9. the Slip forming equipment is also now on site, and the first forms are being placed on the barge (above left). once the floor is cast, the outside walls and interior dividers will be cast by slip forming until the entire block is constructed. Once complete, it will be towed into place, and filler with gravel.
Halterm Pier Expansion Update